A Comparison Between The (Design-Build DB) and (Design-Bid-Build DBB) Approaches Used in the Jordanian Construction Sector and Clarify the Risks Associated with Each Approach

  • Sharaf Al-Deen Waleed AL-Smadi Universiti Putra Malaysia
  • Abdalrahman Hammoudah Yousef Alhndawi Universiti Putra Malaysia
Keywords: Construction Management, Risks, Design-Build, Design-Bid-Build, Construction Safety
Share Article:

Abstract

The continual need for building in developing economies and countries such as Jordan increases the obstacles and problems faced by Project Management Units in completing projects on time, with quality assurance, and at lower prices. However, as more and more new types of project management approaches such as (Design-Bid DB) are introduced, the binding conditions of contracts are growing tougher in order to reduce risks during project execution. In this paper, the researcher tries to provide a fair comparison between (Design-Bid-Build DBB) and (Design-Build DB) approaches which are already used in the construction project in Jordan and offering a good vision for both owners and contractors equally

Downloads

Download data is not yet available.

References

AL-Smadi, S. A.-D. W., Supeni, E. E., & Voon, W. S. (2021). A Study on Safety and Health Good Practices at Construction Sector in Jordan. East African Journal of Engineering, 3(1), 57-71.

Alhusban, M. (2018). Conceptual Procurement Framework for Building Information Modelling Uptake to Enhance Buildings' Sustainability Performance in the Jordanian Public Sector. University of Portsmouth.

Almarri, K., & Abu-Hijleh, B. (2017). Critical Success Factors for Public Private Partnerships in the UAE Construction Industry-A Comparative Analysis between the UAE and the UK. Journal of Engineering, Project & Production Management, 7(1).

Barbosa, F., Woetzel, J., & Mischke, J. (2017). Reinventing Construction: A Route of Higher Productivity. Retrieved from

Bu-Qammaz, A. S. (2015). Risk Management Model for International Public Construction Joint Venture Projects in Kuwait: The Ohio State University.

Chan, A. P., Yeung, J. F., Yu, C. C., Wang, S. Q., & Ke, Y. (2011). Empirical study of risk assessment and allocation of public-private partnership projects in China. Journal of Management in Engineering, 27(3), 136-148.

Chang, A. S., Shen, F.-Y., & Ibbs, W. (2010). Design and construction coordination problems and planning for design–build project new users. Canadian journal of civil engineering, 37(12), 1525-1534.

Creedy, G. D. (2006). Risk factors leading to cost overrun in the delivery of highway construction projects. Queensland University of Technology.

Eastman, C. M., Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2011). BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors: John Wiley & Sons.

El-adaway, I. H. (2008). Construction dispute mitigation through multi-agent based simulation and risk management modeling: Iowa State University.

El-Sayegh, S. M. (2008). Risk assessment and allocation in the UAE construction industry. International journal of project management, 26(4), 431-438.

El-Sayegh, S. M., & Mansour, M. H. (2015). Risk assessment and allocation in highway construction projects in the UAE. Journal of Management in Engineering, 31(6), 04015004.

Fakih, A., & Ibrahim, M. (2016). The impact of Syrian refugees on the labor market in neighboring countries: empirical evidence from Jordan. Defence and Peace Economics, 27(1), 64-86.

Fernandez, R. H. F. (2014). Strategies to reduce the risk of building collapse in developing countries. Strategies.

Goh, C. S., Abdul-Rahman, H., & Abdul Samad, Z. (2013). Applying risk management workshop for a public construction project: Case study. Journal of construction engineering and management, 139(5), 572-580.

Guttiman, D. (2000). Public purpose and private service: The twentieth century culture of contracting out and the evolving law of diffused sovereignty. Admin. L. Rev., 52, 859.

Hale, D. R., Shrestha, P. P., Gibson Jr, G. E., & Migliaccio, G. C. (2009). Empirical comparison of design/build and design/bid/build project delivery methods. Journal of construction engineering and management, 135(7), 579-587.

Heravi, G., & Hajihosseini, Z. (2012). Risk allocation in public–private partnership infrastructure projects in developing countries: case study of the Tehran–Chalus toll road. Journal of Infrastructure Systems, 18(3), 210-217.

Hillebrandt, P. M. (2000). Economic theory and the construction industry: Springer.

Hiyassat, M. A., Alkasagi, F., El-Mashaleh, M., & Sweis, G. J. (2020). Risk allocation in public construction projects: the case of Jordan. International Journal of Construction Management, 1-11.

Kaushik and Sahil, 2017. How to calculate Relative Importance Index using Likert's scale.

Kymmell, W. (2008). Building Information Modeling: Planning and Managing Construction Projects with 4D CAD and Simulations (McGraw-Hill Construction Series): McGraw-Hill Education.

Leahy, J. V., & Whited, T. M. (1996). The effect of uncertainty on investment: Some stylized facts. Journal of Money, Credit and Banking, 28(1), 64-83.

Likhitruangsilp, V., & Harinthajinda, P. (2008). Assessment of contractors' risk response in tunneling projects. Paper presented at the Eleventh East Asia-Pacific Conference on Structural Engineering and Construction, Taipei, Taiwan.

Lines, B., Shalwani, A., & Smithwick, J. (2018). Effectiveness of qualifications-based selection criteria in design-build and construction manager at risk procurements: An empirical analysis. Paper presented at the Construction Research Congress, New Orleans, Louisiana.

Ling, F. Y. Y., Chan, S. L., Chong, E., & Ee, L. P. (2004). Predicting performance of design-build and design-bid-build projects. Journal of construction engineering and management, 130(1), 75-83.

Liu, J., Xie, Q., Xia, B., & Bridge, A. J. (2017). Impact of design risk on the performance of design-build projects. Journal of construction engineering and management, 143(6), 04017010.

Liu, J., Zhao, X., & Yan, P. (2016). Risk paths in international construction projects: Case study from Chinese contractors. Journal of construction engineering and management, 142(6), 05016002.

Nguyen, P., & Likhitruangsilp, V. (2017). Identification risk factors affecting concession period length for public-private partnership infrastructure projects. International Journal of Civil Engineering and Technology, 8(6), 342-348.

Nguyen, P. T., & Nguyen, P.-C. (2020). Risk Management in Engineering and Construction. Engineering, Technology & Applied Science Research, 10(1), 5237-5241.

Öztaş, A., & Ökmen, Ö. (2004). Risk analysis in fixed-price design–build construction projects. Building and environment, 39(2), 229-237.

Reyes, J. P., San-José, J. T., Cuadrado, J., & Sancibrian, R. (2014). Health & Safety criteria for determining the sustainable value of construction projects. Safety science, 62, 221-232.

Sarvari, H., Valipour, A., Yahaya, N., & Noor, N. M. (2014). Risk identification and assessment in Malaysian public-private partnership projects Vulnerability, uncertainty, and risk: Quantification, mitigation, and management (pp. 436-445).

Shrestha, P. P., Migliaccio, G. C., O'Connor, J. T., & Gibson Jr, G. E. (2007). Benchmarking of large design–build highway projects: One-to-one comparison and comparison with design–bid–build projects. Transportation Research Record, 1994(1), 17-25.

Smith, N. J., Merna, T., & Jobling, P. (2014). Managing risk in construction projects: John Wiley & Sons.

Songer, A. D., & Molenaar, K. R. (1996). Selecting design-build: Public and private sector owner attitudes. Journal of Management in Engineering, 12(6), 47-53.

Soomro, F. A., Memon, M. J., Chandio, A. F., Sohu, S., & Soomro, R. (2019). Causes of time overrun in construction of building projects in Pakistan. Engineering, Technology & Applied Science Research, 9(1), 3762-3764.

Tam, W., & Le, K. N. (2006). Environmental assessment by power spectrum. Paper presented at the Joint International Conference on Construction Culture, Innovations, and Management. Dubai, The British University in Dubai.

Wang, T., Tang, W., Du, L., Duffield, C. F., & Wei, Y. (2016). Relationships among risk management, partnering, and contractor capability in international EPC project delivery. Journal of Management in Engineering, 32(6), 04016017.

Zhang, W., & Bai, Y. (2013). Risk allocation and dispute resolution mechanisms in chinese public projects: an empirical study ICCREM 2013: Construction and Operation in the Context of Sustainability (pp. 637-649).

Published
19 October, 2021
How to Cite
AL-Smadi, S., & Alhndawi, A. (2021). A Comparison Between The (Design-Build DB) and (Design-Bid-Build DBB) Approaches Used in the Jordanian Construction Sector and Clarify the Risks Associated with Each Approach. East African Journal of Engineering, 4(1), 1-12. https://doi.org/10.37284/eaje.4.1.442