Technological Factors and Performance of Roads Construction Projects in Nairobi County, Kenya

  • Akuto Musaeh B. P. Kamarkor Kenyatta University
  • Paul K. Sang, PhD Kenyatta University
  • David Nzuki, PhD Kenyatta University
Keywords: Technological Factors, Road Construction, Project Performance, Macroenvironment
Share Article:

Abstract

The successful construction of roads plays a pivotal role in driving Kenya’s economic development, aligning with the objectives outlined in Kenya’s Vision 2030. However, the suboptimal performance of road construction projects in Nairobi County can be attributed to the continually evolving environmental factors. Consequently, this study aimed to explore the relationship between technological factors and performance of roads construction projects in Nairobi County. The theoretical foundations guiding this study encompassed open system theory. Utilizing a positive research philosophy, the study adopted a descriptive and explanatory research design. This research focused on a target population comprising 176 concluded roads construction projects within the Nairobi Metropolitan Area, executed by the Kenya Rural Roads Authority (KERRA). The unit of analysis focused on the completed roads construction projects in Nairobi County. The unit of observation included road engineers, project planners, and directors associated with KERRA, along with road supervisors, inspectors, surveyors, contractors, and members of project implementation teams. Proportional stratified sampling was employed to determine a sample size of 253 respondents. Data collection involved the use of a structured questionnaire. The study embraced descriptive and inferential statistics. The results were presented through tables, and inferential statistics were carried out using linear regression. The study unveiled a positive and significant relationship between technological factors (t=2.270, p<0.05) with project performance. In conclusion, the study establishes a discernible relationship between technological and project performance. The research recommends that managers are urged to embrace digitization and automation, leveraging on technology to address complex technicalities before and during construction

Downloads

Download data is not yet available.

References

Ahmed, M. (2021). Assessing the Performance of Public-Private Partnership Highway Projects: From Anecdotes1Anecdotes to Comprehensive Evidence [Doctoral dissertation, Virginia Tech]. https://vtechworks.lib.vt.edu/handle/10919/104104

An, H., Razzaq, A., Nawaz, A., Noman, S. M., & Khan, S. A. R. (2021). Nexus1Nexus between green logistic operations1operations and1and triple bottom line: evidence from infrastructure-led1led Chinese outward1outward foreign direct investment in Belt and1and Road1Road host countries. Environmental Science and1and Pollution Research, 28(37), 51022-51045.

Assaad, R., El-Adaway, I. H., & Abotaleb, I. S. (2020). Predicting project performance in the construction industry. Journal of Construction Engineering and1and Management, 146(5), 40-52.

Bergeron, F., Croteau, A. M., Uwizeyemungu, S., & Raymond, L. (2020). A framework for research on information technology governance in SMEs. In Start-ups and SMEs: concepts, methodologies, tools, and applications (pp. 1567-1588). IGI Global.

Bertalanffy, L. V. (1968). General systems1systems theory as1as integrating factor in contemporary science. Akten des1 XIV. Internationalen Kongresses1 für Philosophie, 2(2), 335-340.

Chaouk, M., Pagliari, R., & Moxon, R. (2020). The impact of national macro-environmentmacro-environnement exogenous 1 variables1variables on airport efficiency. Journal of Air Transport Management, 82(10), 17-40.

Chileshe, N., Njau, C. W., Kibichii, B. K., Macharia, L. N., & Kavishe, N. (2022). Critical success1success factors1factors for Public-Private Partnership (PPP) infrastructure and1and housing projects1projects in Kenya. International Journal of Construction Management, 22(9), 1606-1617.

Chumba, K. J. (2020). Influence of economic hardship on types1types of violent crimes1crimes among prisoners1prisoners in Uasin Gishu County, Kenya [Doctoral dissertation, Moi University]. http://ir.mu.ac.ke:8080/jspui/handle/123456789/3502

Creswell, J. W. & Clark, V. L. P. (2017). Designing and1and conducting mixed1mixed methods1methods research. New York: Sage publications.

Cytonn (2021). Nairobi Metropolitan Area (NMA) Infrastructure Report 2021. Retrieved1Retrieved at https://www.cytonn.com/topicals/nairobi-metropolitan-area-infrastructure-report

Elong, S., Muhwezi, L., & Acai, J. (2019). Assessment of the Challenges1Challenges and1and Effects1Effects of Delays1Delays in Compulsory Land1Land Acquisition on the Performance of Road1Road Construction Projects1Projects in Uganda. International Journal of Scientific & Engineering Research, 10(9), 1409- 1426.

Fernandes, T., Camerino, O., Garganta, J., Pereira, R., & Barreira, D. (2019). Design and1and validation of an observational instrument for defence in soccer based1based on the Dynamical Systems1Systems Theory. International Journal of Sports1Sports Science & Coaching, 14(2), 138-152.

Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., ... & van Wee, B. (2019). On De-Bunking'n Fake News' in the Post-Truth Era: How to Reduce Statistical Error in Research. Transportation Research Part A: Policy and1and Practice, 126(3), 409-411.

Freeman, R. E. (1984). The politics1politics of stakeholder theory: Some future directions. Business1Business ethics1ethics quarterly, 3(1), 409-421.

Gruden, N., & Stare, A. (2018). The influence of behavioral behavioural competencies1competencies on project performance. Project Management Journal, 49(3), 98-109.

Hair Jr, J., Page, M., & Brunsveld, N. (2019). Essentials of business research methods. Routledge.

Hambrick, D. C., & Mason, P. A. (1984). Upper echelons: The organization as1as a reflection of its1its top managers. Academy of management review, 9(2), 193-206.

Kanyeria, R. N., & Karugu, J. (2020). Influence of External Business1Business Environment on the Success1Success of Health Projects1Projects in Nyandarua County, Kenya. International Journal of Business1Business Management, Entrepreneurship and1and Innovation, 2(1), 1-16.

Kaplan, R. S., & Norton, D. P. (2015). Balanced1Balanced Scorecard1Scorecard Success: The Kaplan-Norton Collection (4 Books). Boston: Harvard1Harvard Business1Business Review Press.

Kenya Roads Board (KRB). (2021). Annual Public Roads1Roads Programme (APRP) 2021/2022. Nairobi: KRB.

Kenya Rural Roads Authority (KeRRA). (2018). Annual Report for Financial Year 2018/2019. KeRRA.

Kenya Rural Roads Authority (KeRRA). (2021). Annual Report for Financial Year 2021/2022. KeRRA.

Kigera, P. M. (2016). Influence of Political Environment on Performance of International Hotel Chains1Chains Operating in Nairobi, Kenya [Doctoral dissertation, University of Nairobi]. http://erepository.uonbi.ac.ke/handle/11295/98571

Lu, J., Ren, L., Zhang, C., Liang, M., Abrhám, J., & Streimikis, J. (2020). Assessment of Corporate Social Responsibility performance and1and state promotion policies: a case study of The Baltic States. Journal of Business1Business Economics1Economics and1and Management, 21(4), 1203-1224.

Mahmud, A. T., Ogunlana, S. O., & Hong, W. T. (2021). Key driving factors1factors of cost overrun in highway infrastructure projects1projects in Nigeria: a context-based1based perspective. Journal of Engineering, Design and1and Technology, 19(6), 1530-1555.

Maina, C., & Gathenya, J. (2014). Influence of economic factors1factors on performance of project management among petroleum marketing firms1firms in Kenya. International Journal of Academic Research in Business1Business and1and Social Sciences, 4(6), 146-152.

Masovic, A. (2018). Socio-cultural factors1factors and1and their impact on the performance of multinational companies. Ecoforum Journal, 7(1) 1-6.

Memon, A. H., Rahman, I. A., & Azis, A. A. A. (2012). Time and1and cost performance in construction projects1projects in southern and1and central regions1regions of Peninsular Malaysia. International Journal of advances1advances in applied1applied sciences, 1(1), 45-52.

Muriithi, W. Z., & Kiiru, D. (2021). Learning organization and1and performance of Kenya Urban Roads1Roads Authority. International Academic Journal of Human Resource and1and Business1Business Administration, 3(10), 29-45.

Musyoka, M. C., Gakuu, C., & Kyalo, D. N. (2017). Influence of Technological Environment on Performance of Gated1Gated Community Housing Projects1Projects in Nairobi County, Kenya. European Scientific Journal, ESJ, 13(3), 11-43.

Mwangi, D. N. (2020). The Critical Role of Participatory Approaches1Approaches on Performance of Major Infrastructure Projects: A Case of Selected1Selected Government (World1World Bank Funded) Projects1Projects in Nairobi, Kenya [Doctoral dissertation, United1United States1States International University-Africa]. https://erepo.usiu.ac.ke/handle/11732/6092

Odhiambo, S. D. (2021). Project Management and1and Implementation of Community-Based1Based Projects1Projects in Siaya County, Kenya [MBA Project, Kenyatta University]. https://ir-library.ku.ac.ke/handle/123456789/23658

Olawale, Y. A., & Sun, M. (2018). Cost and1and time control of construction projects: inhibiting factors1factors and1and mitigating measures1measures in practice. Construction management and1and economics, 28(5), 509-526.

Omondi, K., & Kinoti, K. (2020). Stakeholder participation and1and performance of road1road construction projects1projects in Kilifi County, Kenya. International Academic Journal of Information Sciences1Sciences and1and Project Management, 3(6), 274-292.

Opawole, A., Jagboro, G. O., Kajimo-Shakantu, K., & Olojede, B. O. (2019). Critical performance factors1factors of public sector organizations1organizations in concession-based1based public-private partnership projects. Property Management, 37(1), 17-37.

Owuze, C. A. (2018). Original Paper an Analysis1Analysis of the Socio-Cultural Environment and1and Performance Influences1Influences on Manufacturing Enterprises1Enterprises in Nigeria. Research in Economics1Economics and1and Management, 3(4), 322-343.

Roth, S. (2019). The open theory and1and its1its enemy: Implicit moralisation as1as epistemological obstacle for general systems1systems theory. Systems1Systems Research and1and BehavioralBehavioural Science, 36(3), 281-288.

Rugenyi, F. (2016). Assessment of the influence of project management competence on the triple constraint in projects1projects in Nairobi. International Journal of Academic Research in Business1Business and1and Social Sciences, 6(4), 295-309.

Sabahi, S., & Parast, M. M. (2020). The impact of entrepreneurship orientation on project performance: A machine learning approach. International Journal of Production Economics, 226, 107-121.

San Santoso, D., & Gallage, P. G. M. P. (2019). Critical factors1factors affecting the performance of large construction projects1projects in developing countries: A case study of Sri Lanka. Journal of Engineering, Design and1and Technology, 18(3), 531-556.

Sánchez-Martín, J., Corrales-Serrano, M., Luque-Sendra, A., & Zamora-Polo, F. (2018). Exit for success. Gamifying science and technology for university students using escape-room. A preliminary approach. Heliyon, 6(7).

Scott, P. (2019). General system theory and1and the use of process1process mining to improve care pathways. Applied1Applied Interdisciplinary Theory in Health Informatics: A Knowledge Base for Practitioners, 263(11).

Sirisomboonsuk, P., Gu, V. C., Cao, R. Q., & Burns, J. R. (2018). Relationships1Relationships between project governance and1and information technology governance and1and their impact on project performance. International journal of project management, 36(2), 287-300.

Snyder, H. (2019). Literature review as1as a research methodology: An overview and1and guidelines. Journal of Business1Business Research, 104(3), 333-339.

Van Assche, K., Verschraegen, G., Valentinov, V., & Gruezmacher, M. (2019). The social, the ecological, and1and the adaptive. Von Bertalanffy's1 general systems1systems theory and1and the adaptive governance of social‐ecological systems. Systems1Systems Research and1and BehavioralBehavioural Science, 36(3), 308-321.

Von Bertalanffy, L. (1956). General systems theory. The science of synthesis: exploring the social implications of general systems theory, 103.

Wambui, G. A., & Kisimbii, J. M. (2020). Social-Cultural Determinants1Determinants Influencing the Performance of Community Based1Based Projects1Projects in Kenya: A Case of Kilifi County. Journal of Entrepreneurship & Project management, 4(5), 17-34.

White, P. J., & Johnson, L. A. (Eds.). (2020). Corn: chemistry and technology (No. Ed. 2, pp. 892-pp).

World Bank. (2017). World development report 2017: Governance and the law. The World Bank.

Yamane, T. (1967). Elementary sampling theory. New Jersey: Prentice-Hall.

Zhanglan, Y., Awino, Z. B., & Ogolla, K. (2019). Top management team, macro environment, managerial discretion and1and competitive advantage. International Academic Journal of Human Resource and1and Business1Business Administration, 3(6), 282-298.

Zorić, T., Makitan, V., Brtka, E., & Mrđen, S. (2021). Modern technologies1technologies influence on project success1success factors1factors in IT sector of Serbia. Journal of Engineering Management and1and Competitiveness1Competitiveness (JEMC), 11(2), 124-137.

Published
29 May, 2024
How to Cite
Kamarkor, A., Sang, P., & Nzuki, D. (2024). Technological Factors and Performance of Roads Construction Projects in Nairobi County, Kenya. East African Journal of Business and Economics, 7(1), 217-230. https://doi.org/10.37284/eajbe.7.1.1960